Atacama Minerals Ltd.


Operations Update

First Quarter 2013


Iodine production in the first three months of 2013 ("Q1 2013") was 363 tonnes, a 6% increase over the same period in 2012 ("Q1 2012"), during which iodine production was 344 tonnes. Sirocco is on target with forecast production of 1,600 tonnes for the year. Iodine sales prices averaged $55 per kilogram (Q1 2012: $65) on sales of 217 tonnes. The significant difference between tonnes produced and sold was due to a strike by port workers at someChilean ports in March, effectively delaying the shipment of 108 tonnes of iodine to April. As a result, revenues of approximately $5.6 million which would have normally been recorded in March were not recorded until April when the iodine was ultimately shipped. The Company has estimated the related deferral of after tax profits to be $1.0 million, equivalent to the amount of the loss reported for the quarter.

read more...

Year End 2012

In 2012, the Company achieved strong financial results compared to 2011, with increased production supported by strong iodine prices.
read more...

Third Quarter 2012

In Q3 2012, the Company continued to improve its performance over 2011 with strong production along with solid financial results.
read more...

Second Quarter 2012

Iodine production in the second quarter of 2012 was 338 tonnes, in line with the first quarter of the year and 18% higher than the same period in 2011 (Q2 2011: 286 tonnes). Iodine prices averaged $59 per kilogram (Q2 2011: $36) on sales of 367 tonnes. Production and sale volumes of iodine differ because iodine produced and shipped to customers late in March was recorded as April sales under the Company's revenue recognition policy.

read more...

First Quarter 2012

Following a review of iodine operations in late 2011 and the progressive implementation of operating improvements, significant efficiencies were achieved during the first quarter of 2012, including a 24% increase in iodine production to 344 tonnes compared to the fourth quarter in 2011. Revenues averaged $65 per kilogram (Q1 2011: $29) on sales of 302 tonnes. The difference between production and sale volumes of iodine is due to iodine produced and shipped to customers late in March and recorded as April sales in accordance with the Company's revenue recognition policy.

read more...

Year End 2011

Agitated Leach Plant

Following the appointment of the Management Team, the Company began a review of the ALP to identify ongoing production inefficiencies. As a result, late in the fourth quarter the Company stopped its commissioning efforts to commence modifications to the crushing and screening circuits to enable the plant to operate at 50% capacity. These modifications were completed in February 2012 with the commissioning phase expected to be completed by the end of March. In addition, detailed engineering has started in the crushing and screening circuits to increase throughput to 100% capacity. The implementation and construction phase of this project are scheduled to take place in the second half of 2012.

read more...

Third Quarter 2011

Agitated Leach Plant

Following the appointment of the new management team, a review of the ALP circuit has commenced.

Production Results

Selected operational information for Aguas Blancas mine for the three and nine months ended September 30, 2011 compared to 2010 is set out in the following table:

read more...

Second Quarter 2011

Agitated Leach Plant

The agitated leach plant ("ALP") was modified in late 2010 to handle variable ore types encountered at Aguas Blancas. Modifications to the crushing and screening circuit were successful in providing ore to the leach circuit. Trial runs on the leach circuit indicated that there were modifications required to this section of the plant which have been carried out. Work on the scrubbing circuit remains to be completed. The plant is currently in commissioning and ramp up to full production of 1,500 tonnes of iodine per year is expected to take until late 2011.

read more...

First Quarter 2011

Agitated Leach Plant

During 2010, detailed engineering and construction of the modifications required to the crushing and grinding circuit of the Agitated Leach Plant ("ALP") were completed. In the latter part of the fourth quarter of 2010 the commissioning of the ALP commenced as scheduled. The plant is currently in commissioning and ramp up to full production, which is expected to take until late 2011, when the plant should reach a 1,500 tonne per year rate of iodine production.

read more...

Year End 2010

Agitated Leach Plant

During 2010, detailed engineering and construction of the modifications required to the crushing and grinding circuit of the Agitated Leach Plant (ALP) were completed. In the latter part of the fourth quarter of 2010 the commissioning of the ALP commenced as scheduled and within the budget of $3 million. Ramp up to full production of the ALP is expected to take 6 months. Material from the modified crushing/screening circuit is achieving target size, and the leaching circuit is performing according to design.

read more...

Previous. All pages. Next. Page 1. Page 2

Previous. All pages. Next. Page 1. Page 2

 

Adnet Communications Inc.